Fiscal Year-End is Approaching
Please be Mindful of Key Procurement Dates!
As fiscal year-end approaches, we ask that you submit your year-end requisitions per the following guidance.
Purchase requisitions must be approved in FMS by the following key dates in order to be dispatched by fiscal year-end.
- Friday, September 8 for requisitions >$25K to <$150K
- Friday, September 15 for requisitions < or equal to $25K
- Tuesday, September 19 for eBuy requisitions
We will do all that we can to process your requisitions as quickly as possible. Please note the following:
- Take into consideration the total procurement value, not just the requisition total
- Issuing purchase orders for requisitions >$150K can take 2 to 4 months or more depending on the complexity. Please plan accordingly.
- Approved requisitions received by Procurement after the key dates will be processed only if all approved requisitions submitted prior to the cut-off dates have been processed
- For information and key dates related to FY17 receiving and service accruals, contact your division resource analyst and/or the Fiscal Year-End Close Wiki (click here to access)
Should you have a critical need or an emergency situation after the key dates, please contact the appropriate Procurement Manager:
- Construction – Laura Crosby, lbcrosby@lbl.gov
- Research and Development – Diane Hutchinson, dahutchinson@lbl.gov
- Services – Laura Sanders, lsanders@lbl.gov
- Goods (>$2K) and Technology – Karen Lingua, klingua@lbl.gov
- Goods (<$2K) and PCard Purchases (< $25K) – Heather Pinto, hmpinto@lbl.gov